2022 Street Improvement Project - Construction Update


Friday, November 4, 2022


Street improvements continue along Oak Crest Drive, South Oak Drive and South Oak.

Most recent updates include: 

  • Construction slowed to allow residents to park on the street in front of their house while the concrete curb and gutter cured.
  • Street lighting was maintained and will continue to be turned on at night until homeowners are able to park in their driveways.
  • Grading behind the curb with topsoil was completed.
Looking Ahead:
  • Due to cold weather temperatures, the concrete is taking longer than expected to gain required strength.  We recommend continuing to stay off of the curing concrete.
  • Driveways will be ramped Monday morning and at that time, all homeowners must have their cars parked off the street and in driveways to allow for street grading.
  •  If you will not be able to move your car off the street Monday morning, please contact Heather Cunningham at 651-600-0667 to arrange for alternate parking.

Thank you for your continued patience and understanding, more updates to come!
construction

Sign up for project updates!
Select Notify Me - Street Construction Updates

Project website:

www.cityvadnaisheights.com/2022streetimprovement

Contact

Heather Cunningham
SEH Engineer
651-600-0667 (cell)

hcunningham@sehinc.com


Share on Facebook
Share on Twitter
Share via Email

City of Vadnais Heights
800 East County Road E, Vadnais Heights, MN 55127

Powered by
CivicSend - A product of CivicPlus