2022 Street Improvement Project - Construction Update
Friday, September 23, 2022
This week, Dresel Contracting, Inc., the contractors for the City of Vadnais Heights 2022 Street Improvement Project, continued work at the
Community Park parking lot by removing and replacing concrete curb and gutter and pedestrian ramps. Please be mindful of any barricades and use caution when walking in the area. Next week, the contractor plans to grade the parking lot and prepare it for paving.
We also expect utility improvements to begin next week on
Oak Crest Drive and South Oak Drive. Please note, if at any time your water is discolored, you should flush your line by leaving your cold water running. Once the line has been cleared, your water should return to normal.
Residents will be notified if their driveway will be blocked or if their water is temporarily shut off. There will be disruption, so thank you in advance for your patience. Please keep children a safe distance away from activities. Thank you!