City of Vadnais Heights Logo

2021 Street Improvement Project - Construction Update


Friday, September 10, 2021


This week, T.A. Schifsky & Sons, Inc., the contractors for the City of Vadnais Heights 2021 Street Improvement Project, continued construction. 

The contractor is placing asphalt curb, grading in the green space, and raising iron in the surrounding area at the Bridgewood Park parking lot. On Stockdale Drive they will be removing and placing concrete driveway aprons.  Once an apron has been poured, you cannot drive on it for a week to let the concrete cure so please be patient during this process.

There should always be at least one lane of traffic open on the road so it should not impact any driving access to and from the area. Bridgewood Park will close as necessary for the contractor to perform needed work so please be mindful of signage and barriers in the area. The trail at Kohler Meadows Park is impacted, so please use caution when walking in the area.
 
There will be disruption, so thank you in advance for your patience.  Please keep children a safe distance away from activities. Thank you!

Kohler Park

Sign up for project updates!
Select Notify Me - Street Construction Updates

Project website:

www.cityvadnaisheights.com/2021streetimprovement

Contact

Heather Cunningham
SEH Engineer
651-600-0667 (cell)

hcunningham@sehinc.com


Share on Facebook
Share on Twitter
Share via Email

City of Vadnais Heights
800 East County Road E, Vadnais Heights, MN 55127

Powered by
CivicSend - A product of CivicPlus