2021 Street Improvement Project - Construction Update
Monday, August 23, 2021
Construction continues on Suzanne Court, Suzanne Avenue, Martin Way, and Southwood Drive. With manhole covers and gate valves raised and patched on the roads, they still stick out of the ground more than usual, so please drive with caution.
This week, the contractor will be performing restoration work by laying topsoil and seeding the affected areas. Seed takes time to grow, especially in this dry, hot summer we are having, so please be patient during this time.
The contractor will also continue work at Bridgewood Park and Kohler Meadows Park. They will prep the aggregate base and pave the base course of asphalt on the Bridgewood Park parking lot and the Kohler Meadows Park trail.
There should always be at least one lane of traffic open on the road so it should not impact any driving access to and from the area. Bridgewood Park will remain closed during construction so there will be no access to the park or the pickleball courts. Asphalt trails have not been patched on Rice Street and County Road F so please pay attention to any barriers in the walking lane. The trail at Kohler Meadows Park is also impacted, so please use caution when walking in the area.
There will be disruption, so thank you in advance for your patience. Please keep children a safe distance away from activities. Thank you!