2021 Street Improvement Project - Construction Update Friday, August 6, 2021
This week, T.A. Schifsky & Sons, Inc., the contractors for the City of Vadnais Heights 2021 Street Improvement Project, raised all iron on Suzanne Court, Suzanne Avenue, Martin Way, and Southwood Drive.Now that manhole covers and gate valves are raised and patched, they still stick out of the ground more than usual, so please drive with caution. Next week, the contractor will be clearing the area of any debris, backfilling the new curb to prepare it for topsoil and seed, and patching asphalt driveways. There should always be at least one lane of traffic open, so it should not impact any access to and from the area but please be patient as traffic will be slower. Concrete sidewalk pedestrian ramps on Rice Street will be impacted so please pay attention to any barriers in the walking lane. There will be disruption, so thank you in advance for your patience. Please keep children a safe distance away from activities. Thank you!
|
|
|
|
|
|