Weekly Update - 2020 Construction
Thursday, September 10, 2020
Construction continues for the City of Vadnais Heights
2020 Street Improvement Project, along
Arcade Street, Wildflower Court and Primrose Court. Weather depending, restoration on Arcade Street will begin next week, which includes filling in holes and seeding the black dirt to establish grass growth. This will take time to grow; please be patient. Signing and striping on Arcade Street is likely to begin as well. Please mind the new signs posted as well as the striping.
Once the paint has been placed, please do not drive over the wet paint. Weather depending, concrete will be poured next week and pavement will be rolled at Wildflower Court and Primrose Court. Please stay off of the wet concrete for one week to give it time to cure. All curb and gutter has been poured. Sidewalk access is still effected; please pay attention to any signage posted on walks.
There will be disruption, so thank you in advance for your patience. Please keep children a safe distance away from activities. Thank you!